Question : (From the Initial Stages of Project Development)
Which of the following could be considered stakeholders for a Civil Engineer project? Select ALL that apply.
Correct answer: Contracting Officer
Facility User Communications Squadron Representative Airfield Manager
Question : (From the Initial Stages of Project Development)
Which of the following documents could be considered part of the project record? Select ALL that apply.
Correct answer: Independent Government Estimate
Quality Control Plan Contractor Submittals
Question : (From the Initial Stages of Project Development) A
SABER contractor submits a project invoice to the government that includes rental of a 25K Forklift. The construction inspector for this project clearly recalls that the only forklift used on the jobsite was a smaller 5K forklift, which costs significantly less
- | Page
money to rent. Which document in the project record could be used to dispute this claim?
Correct answer: AF Form 1477 Daily Construction Inspection
Report
Question : (From the Programming Fundamentals Lesson) You
are working on a project and determine a change order is needed because the beams were too small to handle the roof load.However, this would exceed the approval authority for this Construction project. What is a viable option for the project team?
Correct answer: Resubmit the project to obtain appropriate
approval even if work must stop while the approval is obtained.
Question : (From the Programming Fundamentals Lesson) If a
project modifies an existing facility to make it compliant with current codes and regulations, it is likely a(n) _______ project.
Correct answer: Repair
Question : (From the Programming Fundamentals Lesson)
Match the class of cost estimate with its definition and use (not all options will have a match).
- | Page
Correct answer: Class 1: Unit Price Used to negotiate and compare bids with Contractors.
Class 3: Parametric Used for budgeting and making the official
Programmed Amount.
Class 5: Square Foot Used for long range planning when the
scope is still poorly defined.
Question : (From the Programming Fundamentals Lesson)
Determining the Work Classification is one of the most important steps in the programming process, before determining the Fund Source and Program Avenue. Work Classification can
be defined as:
Correct answer: Describing the nature of the work to be
accomplished
Question : (From the Project Management Plan Lesson) Who is
responsible for creating a Project Management Plan?
Correct answer: Project Manager
- | Page
Question : (From the Project Management Plan Lesson) At what
phase in the Air Force project lifecycle should a Project Management Plan be developed?
Correct answer: Planning and Programming
Question : (From the Project Management Plan Lesson) MSgt
Jones is an extremely competent SNCO that has years of experience working on high voltage power projects. You have recently been appointed project manager for a new power line installation on a remote part of your base. Gaining MSgt Jones onto your project team would be an example of which type of risk?
Correct answer: Opportunity
Question : (From the Scoping Project Requirements Lesson)
What is the 'magic question' to collecting stakeholder information?
Correct answer: What are we missing?
Question : (From the Scoping Project Requirements Lesson)
TRUE/FALSE: There are so many digital resources: Sustainment Management Systems, Work Breakdown