- | Page
UTAH CONTRACTOR EXAM
(REAL)QUESTIONS + ANSWERS
GRADED A+
Question : Depreciation is taken on which of the
company's assets?
- Loans
- Current assets
- Fixed assets
- None of the above
CORRECT ANSWER : C ... Explanation: Depreciation is counted from fixed assets.
Question : A private employer who employs __ or more
people as of July 1, 2010, may not hire a new employee unless the employer is registered with and uses a status verification system such as E -Verify to verify the federal legal working status of any new employee.
- 5
- 10
- 15
- | Page
- 1
CORRECT ANSWER : C ... Explanation: A private employer who employs 15 or more people as of July 1, 2010, may not hire a new employee unless the employer is registered with and uses a status verification system such as E -Verify to verify the federal legal working status of any new employee.
Question : If a contractor decides to increase the contract
price, the contractor:
- Should get a loan from the bank
- May request assistance from the subcontractor
- And the owner must agree to a written and signed
- Should request the building inspector to revise the
change order
specifications CORRECT ANSWER : C ... Explanation: A written and signed change order can allow the contractor to change a contract price.
- | Page
Question : If a subcontractor signs an unconditional
waiver and release, this would imply that a:
- Subcontractor cannot ask anything more of the owner
- Owner cannot ask anything more of the subcontractor
- Subcontractor cannot get anything from the prime
- Subcontractor cannot ask anything more of the prime
CORRECT ANSWER : A ... Explanation: Once the subcontractor signs an unconditional waiver and release, the subcontractor cannot ask anything more of the owner.
Question : Any applicant who has been denied a license
to practice on the basis of credentials, or failure to pass a required examination, may submit a request for agency review to the executive director ____ following notification of the denial of a license or refusal to renew or reinstate a license.
- Within 10 days
- Within 20 days
- Within 30 days
- Within 60 days
- | Page
CORRECT ANSWER : C ... Explanation: Any applicant who has been denied a license to practice on the basis of credentials, character, or failure to pass a required examination, or who has been refused renewal or reinstatement of a license to practice on the basis that the applicant does not meet qualifications for continued licensure in any occupation or profession under the jurisdiction of the division may submit a request for agency review to the executive director within 30 days following notification of the denial of a license or refusal to renew or reinstate a license.
Question : What should a contractor do if after starting a
home improvement project the contractor discovers that the details and specifications do NOT correctly show the existing construction?
- Stop and work on a correction
- Stop the job and inform the owner or his agent
- Continue the work if variations are only minor
- Stop the job and inform the Building Department