SWPPP Walmart - Stormwater Exam Questions and Answers Verified by Expert | latest Update

Question : The 1970's law that set into place the regulation of

stormwater is:

Correct answer: The Clean Water Act

Question : Which of the following is never an allowable

stormwater discharge from a construction site?

Correct answer: Discharge from contaminated groundwater

Question : Relative to stormwater permitting, all of the

following must occur before construction starts except:

Correct answer: Submit the notice of termination (NOT)

Question : Of the following factors that influence erosion

rates, the one a contractor has the most control over is:

Correct answer: Groundcover

Question : Common types of erosion include all of the

following except

Correct answer: Sedimentation

Question : Which of the following is NOT a beneficial use of

water?

Correct answer: Flushing a spill down a storm drain

Question : The good housekeeping section of the SWPPP

must include all BUT which of the following

Correct answer: Post construction stormwater management

procedures

Question : Runoff Controls include all but which one of the

following

Correct answer: Rolled Erosion Control Products

Question : Proper spill management should include all of the

following EXCEPT:

Correct answer: Installation of a spill pit on your construction

sites

Question : While inspecting field BMPs, the SWPPP

inspector should perform all of the following EXCEPT:

Correct answer: Assume BMPs are in good condition from a

distance

Question : If your site is inspected by US EPA, or another

regulatory agency, you should:

Correct answer: Be Courteous, Attend their inspection, Allow

access to site and documentation -- All of the above

Question : Potential pollutant sources stored on a construction

site may include

Correct answer: Petroleum storage tanks, soil amendments,

masonry materials -- all of the above

Question : A SWPPP Site Map will show all of the following

except

Correct answer: Notices of Violation

Question : Which of the following information is to be posted

at the entrance to the site?

Correct answer: Construction Site Notice, Permit

authorization, Location of the SWPPP -- All of the above

Question : Requirements for managing stormwater activity on

a construction site are outlined in the following regulation:

Correct answer: NPDES

Question : The Notice of termination can filed when:

Correct answer: All construction activity, inside and outside

the building, is complete and permanent stabilization verified

Question : Which erosion control best mgmt practice

increases water infiltration, dissipates rainfall energy and slows overland flow of stormwater

Correct answer: Vegetation

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration