what option would you choose to let users submit multiple form responses?In the settings tab under form submission select the reload the same form for another submission
Correct ANSWER: In the settings tab under form submission
select the reload the same form for another submission
how can you prefill a value on a field for a user to change if they wish?Set as default value
Correct ANSWER: Set as default value
In the sheet summary you are countng the number of submission that are open, completed and in progress. what is a disadvantage of creating a workflow that moves completed tasks to a resolved/completed sheet?you will loose metrics you may still want to track
- | Page
Correct ANSWER: you will loose metrics you may still want to
track
A form is based on a sheet
Correct ANSWER: a sheet
you want to display the latest comment made for all rows automatically, which column type should you choose?latest comment
Correct ANSWER: latest comment
you have a form showing a status field that should always be set to "not started" when the user submits the form. what is the easiest way that you prevent your users from changing this value?One the form, set the hidden and set the default value to "not started"
Correct ANSWER: One the form, set the hidden and set the
default value to "not started"
- | Page
How do you create a form?Click forms on the menu bar, then click create forms.
Correct ANSWER: Click forms on the menu bar, then click
create forms.
what column type can you use to enumerate row submission for later reference?auto number
Correct ANSWER: auto number
how would you send a quick update for a specific row?select the row(s), then select the send option from the row menu.
Correct ANSWER: select the row(s), then select the send option
from the row menu.
for what purpose would you use groups in Smartsheet?To share an item in workspace
Correct ANSWER: To share an item in workspace
how do you rest the baseline?
- | Page
go to Gant View, click baseline icon in the tool bar, then click reset baseline dialog box.
Correct ANSWER: go to Gant View, click baseline icon in the
tool bar, then click reset baseline dialog box.
how can you send your sheet as an attachment?from the file menu select send as an attachment option.
Correct ANSWER: from the file menu select send as an
attachment option.
how do you add members to a group you created?go to account settings, and click Group Management. Then click the pencil icon to add group members.
Correct ANSWER: go to account settings, and click Group
Management. Then click the pencil icon to add group members.
what are the steps to publish a sheet?click the publish icon on the right toolbar, click the slider for the desired publish option.
Correct ANSWER: click the publish icon on the right toolbar,
click the slider for the desired publish option.