- | Page
QSP EXAM QUESTIONS W ITH
CORRECT ANSWERS
Question :Activities under the CGP include:
- Routine maintenance to maintain original line and grade,
- Disturbances to land surfaces solely related to agricultural
- Clearing and grading 2 acres of land
- Discharges of storm water from areas on tribal lands.
hydraulic capacity, or original purpose of the facility.
operations.
Correct answer:C
Question :Risk Level 2 monitoring requirements include:
- Effluent sampling where applicable
- Sampling for pH and turbidity
- Sampling for pH, turbidity, and suspended sediments
Correct answer:B
Question :All NAL data must be uploaded within ___ after
NAL exceedance has been identified
- | Page
- 24 hours
- 1 week
- 10 days
- 2 weeks
Correct answer:C
Question :Who must file Permit Registration Documents
(PRDs) prior to the commencement of construction activity?
- Qualified SWPPP Developer (QSD)
- Legally Responsible Person (LRP) or the LRP's Approved
- Qualified SWPPP Practitioner (QSP)
- The CEO
Signatory
Correct answer:B
Question :Which regulation establishes a framework for
regulating municipal and industrial storm water discharges to
waters of the United States:
- Clean Water Act (CWA)
- | Page
- Porter-Cologne Water Quality Control Act
- Endangered Species Act
- U.S. Environmental Protection Agency (USEPA)
- California Environmental Quality Act (CEQA)
Correct answer:A
Question :Certain non-storm water discharges may be
necessary for the completion of construction projects.Therefore the General Permit authorizes such discharges
provided they meet the following conditions except:
- Meet the NALs for pH and turbidity
- Not cause or contribute to a violation of water quality
- Comply with BMPs as described in the SWPPP
- Be infeasible to eliminate
- Causes or threatens to cause pollution, contamination, or
standards
nuisance
Correct answer:E
- | Page
Question :When possible, use erosion controls as the ___
protection, with sediment controls as a ___system.
- primary, secondary
- secondary, primary
Correct answer:A
Question :A temporary or permanent structural BMP that
directs concentrated flows away from disturbed areas and prevents erosion is...
- erosion control
- run on/ run off control
- sediment control
Correct answer:B
Question :The amount of eroded soil that settles out at a point
in the watershed that is remote from the origin of the detached soil particles is...
- Rainfall Erosivity Factor
- Slope Length and Steepness Factors
- Soil Cover Factor