PSM 1 - Scrum.org Exam Questions and Verified Answers, 100% Guarantee Pass (Latest 2025) Which does a self-organizing Development Team choose?
- Sprint length.
- How to best accomplish its work
- When to release, based on its progress
- Stakeholders for the Sprint Review
- Product Backlog ordering - Correct Answers ✅A
True or False: The Product Owner makes sure the team
selects enough from the Product Backlog for a Sprint to satisfy the stakeholders
- True
- False - Correct Answers ✅A
The length of a Sprint should be:
- Short enough to keep the business risk acceptable to the
- Short enough to be able to synchronize the development
- No more than one calendar month
- All of these answers are correct - Correct Answers ✅A 1 / 4
Product Owner
work with other business events
PSM 1 - Scrum.org Exam Questions and Verified Answers, 100% Guarantee Pass (Latest 2025) What is the best build structure for Development Teams in order to produce integrated Increments?
- Each Development Team works only on one technical layer
- Each Development Team develops full functionality from
- The Scrum Master, project manager and Development
- The Product Owner and the Development Team
- The Development Team
- The Product Owner and all stakeholders - Correct
of the system (e.g. GUI, database, middle tier, interfaces)
beginning to end throughout all technical layers - Correct Answers ✅A When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected?
Team
Answers ✅A Which two of the following are appropriate topics for discussions during a Sprint Retrospective? (choose the two best answers) 2 / 4
PSM 1 - Scrum.org Exam Questions and Verified Answers, 100% Guarantee Pass (Latest 2025)
- How the team collaborates
- Document acceptance criteria for items in the next Sprint
- The order of items in the Product Backlog
- Identifying high priority process improvements for the next
- Daily Scrum
- Sprint 0
- Release Testing
- Sprint Planning
- Sprint Retrospective
- Sprint Testing
- Release Retrospective - Correct Answers ✅A
Sprint - Correct Answers ✅A Which three of the following are time-boxed events in Scrum?
You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (choose the two best answers) 3 / 4
PSM 1 - Scrum.org Exam Questions and Verified Answers, 100% Guarantee Pass (Latest 2025)
- There should be six Product Owners, reporting to a chief
- Each Scrum Team should have a separate Product Backlog
- There should be six Product Owners, one for each Scrum
- The product has one Product Backlog
- There should be only one Product Owner - Correct
- The meetings and the objectives that a Scrum Team sets
- The Scrum framework being adopted and used properly
- Keeping track of resource allocation
- Managing the performance of the Scrum Team - Correct
Product Owner
Team
Answers ✅A For which is the Scrum Master responsible?
for itself
Answers ✅A
A Sprint Retrospective should be held:
- At the end of each Sprint
- At the beginning of each Sprint
- At the end of the last Sprint in a project or a release