Project Management Module (IFMA FMP) Questions With CORRECT ANSWER s.
Question 1: Which attribute most accurately describes a project?
CORRECT ANSWER : Projects are finite.
Question 2: What is an example of how project managers apply
sound management techniques?
CORRECT ANSWER : they break down a task further if it
remains at the same percent completion despite reported progress.
Question 3: Which is an advantage of using a standardized
project management model?
CORRECT ANSWER : The model is a framework that project
managers can adapt to project specifics.
Question 4: In the project model, what do outputs from the Plan
phase become?
CORRECT ANSWER : inputs to the Execute phase.
- | Page
Question 5: A project will have a long payback period. What
should the project be linked to thus increasing the chances the project will be approved?
CORRECT ANSWER : Strategic facility plans
Question 6: Which activity is set by policy at the start of a
project?
CORRECT ANSWER : Estimating
Question 7: What should a facility manager do at the beginning
of a routine project to achieve success?
CORRECT ANSWER : generate a shared understanding of the
end purpose of a project.
Question 8: What principle is true about the steps involved when
defining project success?
CORRECT ANSWER : Specifying nonessential parameters is as
important as specifying essential ones.
Question 9: Which document may include details such as
adjacency diagrams, space standards, and information on current and future staffing count for business units?
- | Page
CORRECT ANSWER : Statement of requirements
Question 10: In what document would the project manager be
formally listed?
CORRECT ANSWER : Project charter
Question 11: Which is true about the elements in a project
objectives statement?
CORRECT ANSWER : Schedule documentation only includes
milestones for hard delivery dates.
Question 12: An organization gathers data on occupant space
requirements, desired location, and desired cost per square meter (square foot). What other factors should be considered when listing site selection criteria?
CORRECT ANSWER : Desired floor plan/stacking plan and
desired amenities
Question 13: Which element is developed first?
CORRECT ANSWER : Work Breakdown Structure (WBS)
- | Page
Question 14: Of the following terms related to a WBS, which
statement is correct?
CORRECT ANSWER : A task is a function to be performed that
is detailed enough for proposals to indicate cost, schedule, and readiness and completion criteria.
Question 15: In which scheduling methods are as many
activities as possible concurrently performed?
CORRECT ANSWER : Waterfall model scheduling
Question 16: Which statement is true of communications
management for an office relocation?
CORRECT ANSWER : Post-relocation orientation brochures
can help employees find their way around.
Question 17: Which role helps ensure continued senior
management/client support of major projects?