Post Award Contracts Latest 2023

Questions & answers Sep 5, 2025
Loading...

Loading document viewer...

Page 0 of 0

Document Text

DBIA: Principles of Design-Build and

Post Award & Contracts Latest 2023 Miller Act 1935 - Correct Answer Federal Government passed bond requiring payment and performance bonds on all public works, what year?Brooks Bill 1972 - Correct Answer Bill directing A/E's selected on qualifications, what year?Clinger Cohen Act/Defense Procurement Reform Act 1996 - Correct Answer Allows all federal agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing Design-Build.Standard of Care - Correct Answer The level of quality that any average Design Professional would be able to perform given the circumstances.Design Bid Build - Correct Answer Slowest Project Delivery method, linear in nature, prescriptive (owner knows what they want), Multi Prime - Correct Answer Project Delivery - Many contracts through Owner CM at Risk - Correct Answer Project Delivery method allowing the contractor to come on board very early in design for preconstruction services yet maintains separation between Designer and Builder contractually.Design Build - Correct Answer Fastest Project Delivery method, fast tracking possible overlapping design with construction utilizing incremental packages.Low Bid - Correct Answer Procurement Method - Most Familiar Negotiated (Qualifications Based) - Correct Answer Procurement Method - Common for A/E Best Value - Correct Answer Procurement Method - Qualifications and Price Sole Source - Correct Answer Procurement Method - Direct Lump Sum - Correct Answer Contract Format w/ agreed upon fixed price Cost Plus Fee - Correct Answer Contract Format - contractor reimbursed for actual cost plus an agreed upon percentage GMP (Guaranteed Maximum Price) - Correct Answer Contract Format - Combines Cost-Plus & Lump-Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount. 1 / 2

Unit Price - Correct Answer Contract Format - cost per piece Target Price - Correct Answer Contract Format - established cost/benchmark determined jointly by project team.Trust, Flexibility - Correct Answer Successful Design Build requires _____ & _______ between participants Hammurabi - Correct Answer Singular responsibility for both design & construction was first codified by ____ Bridging Documents - Correct Answer Owner provided items such as 20% design or more and provides prescriptive specs at RFP.Spearin Doctrine - Correct Answer Owner is responsible for implied warranties in the sufficiency of the specifications.Performance Requirements - Correct Answer ____ ____ should identify end results.Design Build - Correct Answer Single point of responsibility for both design & construction is an attribute of what delivery method?Substantiation - Correct Answer The process of checking milestones along the way for completeness.Prescriptive - Correct Answer Owner requiring specific products or methods be instituted by DB team in order to achieve desired performance.False - Correct Answer T/F Detailed estimating is the Building systems approach to estimating False - Correct Answer T/F feasibility estimate is cost model and establishes budget for project True - Correct Answer T/F key element of quality assurance is keeping communication lines open between owner and DB True - Correct Answer T/F in Design/cost relationship of DB, the constructor establishes design parameters for architect False - Correct Answer T/F trust is most important thing for DB Schematic estimating - Correct Answer DB estimating sequence where 15%-20% of design is completed

  • / 2

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Questions & answers
Added: Sep 5, 2025
Description:

DBIA: Principles of Design-Build and Post Award & Contracts Latest 2023 Miller Act 1935 - Correct Answer Federal Government passed bond requiring payment and performance bonds on all public works, ...

Get this document $30.00