- If a 500 kV transmission line with a surge impedance
- Generator MVAR output would increase
- All system capacitors would trip off-line
- Generator MVAR output would decrease
- All automatic reactors would connect to the system -
- When system conditions are such that emergency
- Shed firm load
- Implement Active Load Management
- Return outaged equipment to service
- Request a voltage reduction - Correct Answers ✅c.
- If your transmission path is rated for 1200 MW and 1000
loading of 800 MW is currently loaded at 1400 MW, which of the following events would most likely occur?
Correct Answers ✅a. Generator MVAR output would increase
procedures are expected to be implemented, which of the following actions should be considered first?
Return outaged equipment to service
MW are scheduled on it, but due to parallel flows the actual flow is 1300 MW, what action should you take? 1 / 4
NERC PREP TEST 101 EXAM QUESTIONS
AND ANSWERS 100% SOLVED (Newest 2025)
- Request that a phase shifting transformer be installed
- Reduce interchange transactions impacting the path
- Request all parallel flow to PSEs to increase schedules
- Reduce all commercial customer load - Correct Answers
- If your system is MVAR deficient, what action could be
- Raise system frequency above 60.5 Hz
- Shed firm load in the deficient area
- Separate from the Interconnection
- Lower transmission voltages - Correct Answers ✅b.
- Which of the following actions can a system operator take
- Request generators to absorb maximum MVAR
- Place all operating limits on dynamic calculation
- Raise system voltages as high as possible, but within their
✅b. Reduce interchange transactions impacting the path
implemented to prevent voltage collapse?
Shed firm load in the deficient area
in order to maintain stability on the system?
operating parameters 2 / 4
NERC PREP TEST 101 EXAM QUESTIONS
AND ANSWERS 100% SOLVED (Newest 2025)
- Reduce voltages on the transmission system - Correct
- Which of the following actions should you take if an outage
- Open all tie-lines to your neighbor
- Ask the Reliability Coordinator for assistance
- Shed load to mitigate the violation
- Wait for the neighboring system to contact you - Correct
- If a SOL or IROL violation occurs due to transfers across the
- Place all system capacitors in service
- Reduce system load
- Inform the Reliability Coordinator
- Dump firm load - Correct Answers ✅c. Inform the
Answers ✅c. Raise system voltages as high as possible, but within their operating parameters
on a neighboring system has caused a violation on your system?
Answers ✅b. Ask the Reliability Coordinator for assistance
system and it is determined that parallel flows are contributing to the violation, what should the system operator do?
Reliability Coordinator 3 / 4
NERC PREP TEST 101 EXAM QUESTIONS
AND ANSWERS 100% SOLVED (Newest 2025)
- While performing a pre-outage study, you identify that the
- Shed load to mitigate the concern
- Allow the outage to occur and see what happens
- Reschedule the outage if possible
- Allow the outage to take place as long as no load is lost -
- Which of the following actions should the system operator
- Reduce voltages in the area of the violation
- Remove the facility from service
- Curtail any interchange transactions that are curtailable
- Only implement actions if the contingency occurs -
- / 4
transmission outage will cause a thermal violation on a parallel path, which of the following actions would be the first one you would implement?
Correct Answers ✅c. Reschedule the outage if possible
implement first if transmission line limits exceed the facilities emergency limits based on a contingency that has not yet occurred, but their protocols are to respond on a pre- contingency basis?
Correct Answers ✅c. Curtail any interchange transactions that are curtailable