NERC Exam Study Questions Emergency Preparedness Questions With Complete Solutions

Q1: For the annual test of an entity's back-up functionality

Operating Plan to be valid, it must demonstrate which of the following?

  • Back-up functionality is maintained for at least 2
  • continuous hours

  • All shift personnel are comfortable at the backup site
  • Transition time is one hour or less
  • The backup site is secure - Correct Answers ✅A) Back-
  • up functionality is maintained for at least 2 continuous hours

Q2: A BA is experiencing low voltage in the northeast region.

A 50 MVA generator in that area is loaded at 50 MWs. What action could a System Operator take to increase the voltage in that area?

  • Increase generation to overload capacity
  • Decrease reactive power until voltage increases
  • Do nothing; the AVR will take care of it
  • Decrease real power and increase reactive power -
  • Correct Answers ✅D) Decrease real power and increase reactive power

Q3: Maintenance in the area has resulted in the ICCP

communication line being cut to the control room. Which of the following actions is most appropriate?

  • Implement the plan for Loss of Control Center Functionality 1 / 2

NERC Exam Study Questions Emergency Preparedness Questions With Complete Solutions

  • Manually update State Estimator with the most current
  • information

  • Report the loss of ICCP to NERC
  • Switch AGC to Flat Frequency Control - Correct Answers
  • ✅C) Report the loss of ICCP to NERC

Q4: A portion of a Reliability Coordinator Area is experiencing

low voltage. What Operating Instructions should the RC issue?

  • Lower transfers across area and decrease generation
  • Increase transfers across area and decrease generation
  • Lower transfers across area and increase generation
  • Increase transfers across area and increase generation -
  • Correct Answers ✅C) Lower transfers across area and increase generation

Q5: Interconnection frequency is at 59.85 Hz. The System

Operator has not experienced any disturbances. What does this indicate?

  • Interconnection voltage and load are not balanced
  • Interconnection system loads are higher than on-line
  • generation

  • Collective system generation is higher than system load
  • A loss of load - Correct Answers ✅B) Interconnection
  • system loads are higher than on-line generation

  • / 2

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Study Guides
Added: Aug 1, 2025
Description:

NERC Exam Study Questions Emergency Preparedness Questions With Complete Solutions Q1: For the annual test of an entity's back-up functionality Operating Plan to be valid, it must demonstrate which...

Get this document $30.00