who shall the special inspector demonstrate competence to?
a.)contractor b.)engineer c.)architect d.)building official - CORRECT ANSWER -d.) building official
who can issue a stop work order?
a.)registered design professional b.)building official c.)contractor d.)owner - CORRECT ANSWER -b.)building official 1 / 3
- | P a g e
what type of inspection is required for post-installed adhesive anchors (epoxy) placed in a horizontal position in to an existing 4000 psi concrete wall?
a.)no inspection is required b.)periodic special inspection c.)continuous special inspection d.)city inspection only - CORRECT ANSWER -c.) continuous special inspection (IBC table 1705.3)
Which of the following does not need to be on a daily report containing nonconforming items?
a.)description and location b.)name of each individual notified and method of notification c.)proposed solution from the special inspector d.)reference to the detail or specification that is not being followed - CORRECT ANSWER -c.) a proposed solution from the special inspector
discrepancies should be brought to the immediate attention of the 2 / 3
- | P a g e
a.)city inspector b.)engineer c.)contractor d.)architect - CORRECT ANSWER -c.) contractor
foundation walls built per table 1807.1.6.2 require what extent of special inspection?
a.)periodic for rebar and continuous for concrete placement b.)none for rebar and continuous for concrete c.)continuous for rebar and concrete placement d.)none at all - CORRECT ANSWER -d.) none at all (IBC 1705.3 Exception #4)
who must a special inspector notify of their presence on a jobsite?
a.)engineer b.)building official c.)contractor d.)icc - CORRECT ANSWER -c.) contractor