- | Page
CM 4221 FINAL EXAM QUESTIONS
AND ANSWERS | LATEST UPDATE|
ALREADY PASSED
Question 1: Which of the following is not a method used
to procure a constructor?
- None of these
- Best value
- Job order contracting
- Low bid
- Qualifications-based selection
CORRECT ANSWER : c. Job order contracting
Question 2: Which management activity listed below is
where the project manager is tasked with coordinating subcontractors, planning sequences of construction, and developing effective communication?
- None of these
- Controlling
- Organizing
- | Page
- Scoping
- Planning
CORRECT ANSWER : c. organizing
Question 3: This testing process helps to reduce the risk
that major project systems (HVAC, electrical, etc) will work according to the project objectives, plans, and specifications.
- Commissioning
- As-builts
- None of these
- Notice to Proceed
- Constructability review
CORRECT ANSWER : a. commisioning
Question 4: Vertical building projects are first designed
by an architect and then engineered by design engineers while horizontal infrastructure projects are typically designed and engineered by design engineers.True
- | Page
False
CORRECT ANSWER : True
Question 5: Based on laws and regulations, privately
financed projects must utilize competitive bidding to procure a construction firm.True False
CORRECT ANSWER : False
Question 6: An agency construction manager firm is
contracted with the Owner, lead designer, and construction firm on a project.True False
CORRECT ANSWER : false
Question 7: A program manager is the same as a project
manager.True
- | Page
False
CORRECT ANSWER : false
Question 8: During the early stages of the engineering and
design phase of a project, the Owner typically procures the lead design firm using qualifications-based selection.True False
CORRECT ANSWER : true
Question 9: What is the definition of a project delivery
system?
- The process by which the feasibility of a project is
- None of these
- The contractual relationships that exist between project
- The method of procuring a constructor to build a
determined
team members