CLC 059 TEST QUESTIONS &

ANSWERS(RATED A)

Question : If. during pre-award. the Acquisition Team

decided to include government property. What impact will that have on the contract. post-award? (Select two that apply.)

Correct answer: "The prime contractor must conduct

periodic reviews of its subcontractors' property control systems.

The prime contractor must flow down the applicable government property clauses to its subcontracts.

"

Question : Which of the following are key. recommended

resources for subcontracting compliance management?(Select two that apply.)

Correct answer: "Small Business Administration (SBA)

website

  • | Page

DoD Office of Small Business Programs (OSBP) website

"

Question : Which olthe following contracts is required to

submit a small business subcontracting plan? Each contract has subcontracting possibilities.

Correct answer: $1 million services contract awarded to

another than small business.

Question : "The Defense Contract Management Agency

(DCMA) Property Administrator Team completed its review of a prime contractor's property system. The Team found that the prime contractor's property records included government -furnished property and omitted contractor- acquired government property. The Team found that the prime contractor flowed down the applicable government property terms and conditions to its subcontracts. The Team found that the prime contractor

  • | Page

did not perform periodic reviews of its subcontractors' property systems. The Team found !that the prime contractor's maintenance program included normal and routine preventative maintenance and repair. Based on the Property Administrator Team's findings and the property system criteria in FAR 52.245-1. how many significant deficiencies are included in the Team's f indings?"

Correct answer: 2

Question : "A prime contractor has complied with all but

two of the small business participation requirements in its small business participation commitment document

  • SBPCD). The prime contractor recently sent you a
  • corrective action plan that details the practical efforts the prime contractor will take to meet these two requirements. You are assessing the prime contractor's pertonnance in the Small Business Subcontracting Section of the Contractor Pertormance Assessment Reporting System (CPARS). What will you do now? To answer this question. feel free to refer to FAR 42.1502.Table 42 2. Evaluation Rating Definitions. (Select two that apply.)"

  • | Page

Correct answer: "Include an objective. detailed narrative

thal explains and supports lhe evaluation rating you assign.

When assessing the prime contracto(s performance.consider if ii made a good faith effort to meet ils small business subcontracting goals and requirements.

"

Question : "The Contractor Purchasing System Review

(CPSR) Team completed its review of a p rime contractor's system for subcontracting. The Team found that the prime contractor maintains an organization plan that clearly delineates responsibility and authority. The Team found that some mandatory flow-down clauses were not included in applicable subcontracts. The Team found that procedures are in place to ensure the proper types of subcontracts are selected. The Team found no

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration