CCMP Exam Questions and Answers 100% Correct
Question : What is the most common risk factor for a
successful change implementation?
- Uncertain implementation timelines
- Vague project plan
- Stakeholder resistance
- A change in sponsorship
Correct answer: c. Stakeholder resistance
Question : What is meant by "What's in it for me?" with
regard to a change management communication strategy?
- The change manager should read the communication plan
- Project team members want to understand how many hours
- Stakeholders want to be sure they are recognized in the
- People want to understand how the change will impact
carefully
they should spend on communication
change newsletter
him/her individually
Correct answer: d. People want to understand how the change
will impact him/her individually
Question : What should happen after a successful change
effort implementation?
- Sustainment through strategic planning and regular goal
- Sustainment through ongoing communication and metrics
- Communication of change objectives being met and
- Dissolve the change management team
review
tracking
recognition of change sponsors
Correct answer: b. Sustainment through ongoing
communication and metrics tracking
Question : As a change leader, what is the first step you must
ensure happens when executing the learning and development plan?
- Sponsors are booked for the training
- Reservations or bookings are made for training rooms
- The curriculum is delivered according to plan
- Learning materials have been developed
Correct answer: d. Learning materials have been developed
Question : What is a key condition for change management
closure?
- Appropriate operational owners have approved the transfer
- A comprehensive stakeholder satisfaction survey has been
- The sponsor has completed an independent evaluation of
- The funds allocated to the project are spent and no further
of change outcomes to their areas
conducted and assessed
the change management program
allocation is anticipated
Correct answer: a. Appropriate operational owners have
approved the transfer of change outcomes to their areas
Question : Which of the following may be incorporated into
the contract? 1.) bid documents 3.) Letters, change orders and specifications. 4.) SOWs, SLAs, RFP, procedures and prices
Correct answer: 1,3,4
Question : Which of the following are possible outcomes of
an RFI process? 2.) Decision to make 3.) Send the project out under an RFP 4.) Kill the project
Correct answer: 2, 3, 4
Question : Which of the following statements about dispute
resolution is/are true? 2.) the legal system will resolve the dispute unless there is agreement on a dispute revolution plan
Correct answer: 2
Question : which of the following possible impacts of a
contract change on performance are ordinarily true? 1.) may improve or get worse 2.) KPIs may change or new KPIs established 4.) new SLAs may need to be established.
Correct answer: 1, 2, 4
Question : Who can initiate a change request? 1.) the
customer 2.) the supplier