Question : Sampling from a mixer/truck agitator- Where is

sample taken?

Correct Answer: Between 10% and 90% (Not when testing

with Super P)

Question : How is a sample taken when sampling plastic

concrete?

Correct Answer: Either pass a receptacle completely through

a discharge stream OR divert a discharge stream completely into a sampling container.

Question : How many grab samples are needed when testing

for uniformity of samples?

Correct Answer: 3

Question : What size sample is needed when casting 3

100mm x 200mm cylinders?

Correct Answer: Minimum 20L

  • | P a g e

Question : What size sample is needed when casting 150mm

x 300mm cylinders?

Correct Answer: Minimum 30L

Question : What size sample is needed when casting 150mm

x 150mm x 535mm beams?

Correct Answer: Minimum 55L

Question : How much extra sample is needed when more than

  • cylinders/specimens are to be cast?

Correct Answer: Volume of the cylinders/specimens plus

10% extra

Question : How much time is allowed for obtaining,

transporting and remixing the sample?

Correct Answer: 10 minutes

Question : A sample contains aggregate larger than that

appropriate for the size of the moulds or equipment.

Correct Answer: It must be wet-sieved prior to testing

Question : Information required on reports

  • | P a g e

Correct Answer: Conc mix no, Sample source, Batch

time/date, Sample time/date, Project site, Sample location if different, Location of conc in structure, Technician name, Lab name/address, Signature of test report reviewer, Any deviation from test procedures

Question : Air Content

Correct Answer: The volume of air voids of plastic concrete,

exclusive of pore space in aggregate particles, determined through observations of the change of air volume in concrete with a change in pressure.

Question : Slump

Correct Answer: A measure of consistency of freshly mixed

hydraulic cement concrete, equal to the subsidence, measured to the next 5mm, of the moulded substance immediately after the removal of the slump cone

Question : Slump Flow

Correct Answer: The horizontal spread of concrete

immediately upon removal of the slump cone as a measure of the unconfined fluidity of concrete giving a relative degree of indication of the degree to which concrete can travel

  • | P a g e

Question : How many water-to-cementing materials ratios are

needed for concrete trial mixes?

Correct Answer: 3

Question : What temperature is considered stable before

mixing concrete?

Correct Answer: 23 C +/- 2 C

Question : Where should cementing materials be stored?

Correct Answer: In a dry place, in moisture-proof containers

Question : What sieve must cementing materials be passed

through before use to reject lumps?

Correct Answer: 1.25mm or finer

Question : Surface moisture in fine and coarse aggregate

should be obtained using samples of what size?

Correct Answer: 500g-1000g

Question : How much time is spent mixing concrete?

Correct Answer: Mix 3 minutes, rest 3 minutes, mix 2

minutes

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Study Guides
Added: Aug 14, 2025
Description:

CCIL EXAM NEWEST VERSION COMPLETE 100 QUESTIONS AND CORRECT DETAILED ANSWERS Question : Sampling from a mixer/truck agitator- Where is sample taken? Correct Answer: Between 10% and 90% (Not when te...

Get this document $30.00