APM PMQ EXAM QUESTIO NS AND

ANSWERS 100% ACCURAT E!

Question : What should a business case include?

Correct answer: B - Background

O - Options B- Benefits CA - Commercial Aspects R - Risks T - Timescales

Question : What are the 5 aspects of the PRAM?

Correct answer: Initiate

Identify Assess Plan responses Implement responses

  • | Page

Question : What are the 5 phases in the extended project

life cycle?

Correct answer: Concept

Definition Development Handover and Closure Operations

Question : Who are potential stakeholders within a

project?

Correct answer: Project Sponsor

Project Team Users Suppliers Customers Senior Management

Question : What are the 5 steps within the information

management process?

  • | Page

Correct answer: Collection

Storage Dissemination Archiving Destruction

Question : What are the steps of the requirements

management process?

Correct answer: Capture

Analyse Justify Baseline

Question : What are the steps of the change control

process?

Correct answer: - Submit Change Request

Review viability of taking request further

  • | Page

Assessment of feasibility and impact of the proposed change

Decision

Question : What are potential sources of change?

Correct answer: Internal:

Technical Error

Incorrect Estimate

Resourcing Issues

External:

Business Justification

Requirements change

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration