Question 1: Which of the following documents is utilized
for correspondence between the A/E or Owner and the Contractor?
- Job Diary
- Memorandum
- Construction Report
- Formal Business Letter
CORRECT ANSWER: d
Question 2: Which of the following documents is used for
correspondence between the home office and the job site?
- Job Diary
- Memorandum
- Construction Report
- Formal Business Letter
- | Page
CORRECT ANSWER: b
Question 3: What is the best time to distribute the
Working Agenda to the Participants?
- As a follow-up to the meeting
- At the beginning of the meeting
- About one day after the meeting
- About one day prior to the meeting
CORRECT ANSWER: d
Question 4: Which document describes the Suggested
Agenda for the Preconstruction Meeting?
- General Conditions
- General Requirements
- Technical Specifications
- Supplementary Conditions
- | Page
CORRECT ANSWER: b
Question 5: What is the best time to distribute the
Meeting Minutes to the Participants?
- At the beginning of the meeting
- About one day after the meeting
- About one hour prior to the meeting
- About one day prior to the meeting
CORRECT ANSWER: b
Question 6: Which of the following descriptions are the
primary content items for the meeting minutes?
- To, from, project, date, time place and subject
- Purpose, specific objectives, time frame, topical
- Objective clear and measurable, attendance, role of
- Attendance, topical headings with paragraph stating
headings with paragraph, role
each person, their expertise
person assigned, completion
- | Page
CORRECT ANSWER: d
Question 7: Which of the following descriptions are the
content items for the working agenda?
- Plan with goals and specific activities, priority, time
- Purpose, specific objectives, time frame, topical
- Activity description, days, information needed crew
- Attendance, topical headings with paragraph stating
needed, scheduled events
headings with paragraph, role
size, material & equipment
person assigned, completion
CORRECT ANSWER: b
Question 8: What are the mental activities that must be
taken into consideration for each topic during the planning phase of a meeting?