ACG CxA Exam Prep Questions and

Study Guides Aug 18, 2025
Loading...

Loading document viewer...

Page 0 of 0

Document Text

ACG CxA Exam Prep Questions and Answers 100% Correct

Question: Identify typical team members of the Cx Team.

  • Owner, End user, Architect
  • Electrical engineer, Mechanical engineer, Commissioning
  • authority

  • Controls contractor, Mechanical contractor, Electrical
  • contractor

  • Sheet metal contractor, TAB agency, General or
  • construction manager

  • Owners O&M staff

Correct answer: a, b, c, d, e

Question: Comprehensive Commissioning starts at which

phase of a building project?

Correct answer: Pre-design phase

Question: Comprehensive Commissioning continues through

which phase?

Correct answer: Post-acceptance phase

Question: What opportunity does Comprehensive

Commissioning provide among design and construction team members?

Correct answer: Cultivates a quality management focus

Question: Which Chapter of the ACG guideline identifies

detailed methodology for Comprehensive HVAC Commissioning?

Correct answer: Chapter 5

Question: What are the Comprehensive Commissioning

phases?

Correct answer: Pre-design, Design, Construction,

Acceptance, Post Acceptance

Question: In the Comprehensive Commissioning Pre-design

phase, what is established as an integral part of the project?

Correct answer: Commissioning

Question: In the Comprehensive Commissioning Pre-design

phase, who selects the commissioning authority?

Correct answer: The owner

Question: In the Comprehensive Commissioning Pre-design

phase, what is developed?

Correct answer: Scope of commissioning

Question: In the Comprehensive Commissioning Pre-design

phase, what does the commissioning authority review?

Correct answer: Design intent document

Question: In the Comprehensive Commissioning Design

phase, what is reviewed to ensure it accommodates commissioning?

Correct answer: Design

Question: In the Comprehensive Commissioning Design

phase, what is written to define contractor responsibilities?

Correct answer: Commissioning specifications

Question: In the Comprehensive Commissioning Design

phase, who writes the commissioning plan?

Correct answer: Commissioning authority

Question: In the Comprehensive Commissioning Design

phase, what is established?

Correct answer: Project schedule

Question: In the Comprehensive Commissioning

Construction phase, what does the commissioning authority review?

Correct answer: Contractor submittals

Question: In the Comprehensive Commissioning

Construction phase, what does the commissioning authority update?

Correct answer: Commissioning plan

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Study Guides
Added: Aug 18, 2025
Description:

ACG CxA Exam Prep Questions and Answers 100% Correct Question: Identify typical team members of the Cx Team. a. Owner, End user, Architect b. Electrical engineer, Mechanical engineer, Commissioning...

Get this document $30.00