ACG CxA Exam Prep Questions and Answers 100% Correct
Question: Identify typical team members of the Cx Team.
- Owner, End user, Architect
- Electrical engineer, Mechanical engineer, Commissioning
- Controls contractor, Mechanical contractor, Electrical
- Sheet metal contractor, TAB agency, General or
- Owners O&M staff
authority
contractor
construction manager
Correct answer: a, b, c, d, e
Question: Comprehensive Commissioning starts at which
phase of a building project?
Correct answer: Pre-design phase
Question: Comprehensive Commissioning continues through
which phase?
Correct answer: Post-acceptance phase
Question: What opportunity does Comprehensive
Commissioning provide among design and construction team members?
Correct answer: Cultivates a quality management focus
Question: Which Chapter of the ACG guideline identifies
detailed methodology for Comprehensive HVAC Commissioning?
Correct answer: Chapter 5
Question: What are the Comprehensive Commissioning
phases?
Correct answer: Pre-design, Design, Construction,
Acceptance, Post Acceptance
Question: In the Comprehensive Commissioning Pre-design
phase, what is established as an integral part of the project?
Correct answer: Commissioning
Question: In the Comprehensive Commissioning Pre-design
phase, who selects the commissioning authority?
Correct answer: The owner
Question: In the Comprehensive Commissioning Pre-design
phase, what is developed?
Correct answer: Scope of commissioning
Question: In the Comprehensive Commissioning Pre-design
phase, what does the commissioning authority review?
Correct answer: Design intent document
Question: In the Comprehensive Commissioning Design
phase, what is reviewed to ensure it accommodates commissioning?
Correct answer: Design
Question: In the Comprehensive Commissioning Design
phase, what is written to define contractor responsibilities?
Correct answer: Commissioning specifications
Question: In the Comprehensive Commissioning Design
phase, who writes the commissioning plan?
Correct answer: Commissioning authority
Question: In the Comprehensive Commissioning Design
phase, what is established?
Correct answer: Project schedule
Question: In the Comprehensive Commissioning
Construction phase, what does the commissioning authority review?
Correct answer: Contractor submittals
Question: In the Comprehensive Commissioning
Construction phase, what does the commissioning authority update?